* Water Treatment Plant Up-Grade:

* Red Hill / Rt. 50 Sewage collection Project:  

* Misc. Improvements Water Project # 2  Riser Ridge, Volcano, Borland Springs, Jerico Road, Doyle Dry Run Road, Oak Grove Road, Ewing Ridge, Shiloh-Tallyho, Laurel Fork.

    

 

Last updated NOVEMBER 5, 2004


 

 

 

Misc. Improvements Project # 2                         Updated February, 2004

 

The District has contracted the Engineering firm of Cerrone Associates, located in  Wheeling, WV  to design  a water line extension project.

The project serves Riser Ridge, Volcano, Borland Springs, Jerico Road, Doyle Dry Run Road, Oak Grove Road, Ewing Ridge, Shiloh-Tallyho, Laurel Fork.

The project  will consist of, twenty seven miles of water line and serves an estimated 295 new customers, at an estimated cost of $3,650,000.

The project is currently in the early design stage.

For more Information call the District office @ 422-6042

Updates will be posted to this web page as they become available. 

  

Please check back !!

 


Water Plant Up-Grade                           Updated February 5, 2004

The District has contracted the Engineering firm of Cerrone Associates, located in  Wheeling, WV to design a plain for an upgrade to increase the capacity of the water treatment plant located on Davisville Road.

This project is needed to meet increased water consumption both in the Claywood Park Public Service District, as well as Mineral Wells Public Service District, The Town of Elizabeth and to meet new mandates of the Safe Water Drinking Act.

We will increase the capacity of our existing treatment plant from 1.7 MGD (Million Gallons per Day) to 4.3 MGD.

Funding for the project will come from the U.S. Dept. of Agriculture, Rural Utility Service. in the amount of $ 4,425,000.   The District will receive a loan in the amount of $ 4,175,000 and a grant for $ 250,000. also from  Rural Utility Service.

Design is Approx 95% complete.

Updates will be posted to this web page as they become available.   

Please check back !!

 

 


Red Hill / Rt. 50 Sewage Project                            Updated November 5, 2004

The District has contracted the Engineering firm of Cerrone Associates, located in  Wheeling, WV to design  a Sewer collection extension project, for the Red Hill, Winding Road ,Dutch Ridge and  Mill Run Road areas of our District. .

The new collection system will consist of gravity flow and pressure main's, Grinder pump's will be utilized where gravity flow is not applicable.

The design plans, has been submitted to the  West Virginia Department of Environmental Protection (WV,DEP), and the West Virginia Public Service Commission.

We must get approval from both of these agencies before construction can begin.

Design is 100% complete.

After the approval of the plans, then funding for the project can be pursued.

There will be approximately 470 potential customers to be supplied with sewer service in this project area.

Thursday November18th 2004, The District will hold a public meeting at the Free Will Baptist Church on

Winding Road, from 5:30pm until 8:00pm, concerning the sewage collection project that is under way for the

property owners of Winding Road, Red Hill, Scenic Hills, George Washington and the Mill Run Road areas.

As well as the property owners on Dutch Ridge Road currently not served with public sewer.

System Design maps and right-of-ways will be on hand for your review.  All property owners in these areas

are urged to attend.

Updates will be posted to this web page as they become available.